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
Conclusion of Djelibakoro Well Project – Guinea
TWVycml3ZWF0aGVyK1NhbnM6MzAw
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

The project to build a well in Djelibakoro has been completed under the direction of Returned Peace Corps Volunteer Shreyan Sen.
A deep borehole was drilled and a pump was installed. Piping was placed in the well, and it was sealed. A concrete slab, drainage channel, and soak pit were installed to keep the area free of standing water.
To read about the beginning of the project, CLICK HERE.
Shreyan reports:
The contractor conducted a site assessment and then completed drilling within a matter of 10 days.
The village is very happy with the end result, as can be seen from the attached Letter of Appreciation.
We are grateful to Shreyan for completing this important project.